Skip to content
R.S.E. Projects Private Limited logoR.S.E. PROJECTSPRIVATE LIMITED
All newsProject Update

R.S.E. Projects commissions a 132 KV substation in Punjab

R.S.E. Projects

The team completed erection, testing and charging of a 132/33 KV substation, handing the asset over with a full commissioning record set.

Our commissioning crew energised a 132/33 KV substation after completing the full pre-commissioning protocol — transformer ratio and tan-delta testing, breaker timing, CT/PT verification and end-to-end protection scheme checks.

Scope executed

  • Erection of power transformers, breakers and isolators
  • Control & relay panel wiring and termination
  • Complete testing and calibration of primary and secondary equipment
  • Statutory liaison and charging clearance

The asset was handed over with as-built drawings, test records and O&M manuals in a single documented set.

Commissioning132 KVPunjab