Every hour of an unplanned overrun is production lost, and the overrun is almost never caused by the work itself. It is caused by something that was not ready when the plant went off.
Decide the scope before you decide the window
List every task, not the ones you expect to matter. Each entry needs an owner, a duration, a predecessor and the materials it consumes. Anything that can be done live should be moved out of the shutdown entirely — that alone often shortens the window by a shift.
Materials on site, verified, before the outage
Not ordered. Not dispatched. On site, unpacked and checked against the specification. A wrong-rated contact set discovered at hour two costs the whole window.
Permit-to-work discipline
Isolation points identified and tagged, earthing applied and recorded, and one named person controlling the permit. Where the shutdown is partial, the boundary between dead and live sections must be physically obvious to a tired crew at 3 a.m.
Staff for the schedule you wrote
Round-the-clock work needs crews that rotate, not crews that stay. Testing instruments and their operators are the usual bottleneck: erection can be parallelised, testing frequently cannot.
Close the punch list before restart, not after
Items deferred past re-energisation tend to stay deferred until the next shutdown. Thermography on the first load is the cheapest test in the whole exercise and catches loose terminations before they become an outage.